Maintenance of Medium Voltage Substation
ECHEDORO - THESSALONIKI
Maintenance of Medium Voltage Substation














Within the framework of the implementation of the project UPGRADING OF SUBSTATIONS and BUILDING WORKS at the HELLENIC STEEL plant, the following works were carried out:
- Replacement of Medium Voltage Substation
- Maintenance of 8 Medium Voltage Substations
- Medium Voltage Field Sandblasting
- Replacement of medium voltage cables
- Measurements of Medium Voltage Substations
- Painting of Medium Voltage Areas
Project Location
ECHEDORO - THESSALONIKI
Type of project
Industrial Projects